Tag Archives: business

Current status: limited open (part 2)

It’s been two weeks since we officially opened our doors. We are open every day of the week, training our staff, and getting people floating! Currently our appointment times are:

Monday – Thursday: 3pm, 5pm, 7pm

Friday: 1pm, 3pm, 5pm, 7pm

Saturday: 7am through 9pm on the odd hours. Last appointment starts at 9pm.

Sunday: 11am, 1pm, 3pm, 5pm

As of this writing, we are booked through April 20th. We will expand our hours ASAP. In the meantime, you may book your future float through our online calendar (hover over the date to see the popup calendar for a specific date) or ask to be added to our automated wait list.

Current status: limited open

Get ready to float!

We’re opening our calendar in stages, starting Wednesday, February 25th. In our crowdfunding campaign last fall, we promised our backers that they could get in to the tanks first. So:

1) First shot goes to our crowdfund backers: check your email at noon on Wednesday the 25th.

2) Everyone who preordered should check their email at noon on Saturday the 28th.

Our calendar will be open to everyone on Wednesday, March 4th!

Thank you, everyone, for your patience and ongoing support! It means so much to us.

Construction progress 3

The shop is taking shape!  Our walls are up, the ceiling is going in, and the showers are getting fitted out.  We spent last weekend in there painting, and will probably be in for two more weekends of painting before we’re done.

Reception desk and insulated wall
Our reception area, showing the insulated wall of one of the float rooms. We have thick interior walls: heavy OSB panels, insulation and doubled thickness of drywall, all to minimize sound transmission.

Continue reading Construction progress 3

Construction progress 2

A piece of bad news to lead off with: after delays with inspections, some extra work from surprises in the walls, and scheduling problems over the holidays, our contractors our now saying they expect to be finished in early February.

The work so far is looking great, though.  Electrical and plumbing roughin inspections are both signed off, and we’ll be closing up the walls next week.

For several days after the electricians started, there were tangles of armored cable everywhere, like Doctor Octopus had just lost a fight.
For several days after the electricians started, there were tangles of armored cable everywhere, like Doctor Octopus had just lost a fight.

 

Float tank delivery
Our first two new float tanks arrived in the rain right before Christmas.

Continue reading Construction progress 2

Job listing: float tank operator

EDIT: This posting has been filled.

We’ve just posted our first job listing:  we need a part time float operator to begin when we open in early January.   If you’re enthusiastic about floating and have some aptitude for friendly customer service, please check out the details and send us your resume.  Don’t worry if you haven’t floated before – we’ll teach you that part.  We look forward to working with you in the new year!