Current status: limited open (part 2)

It’s been two weeks since we officially opened our doors. We are open every day of the week, training our staff, and getting people floating! Currently our appointment times are:

Monday – Thursday: 3pm, 5pm, 7pm

Friday: 1pm, 3pm, 5pm, 7pm

Saturday: 7am through 9pm on the odd hours. Last appointment starts at 9pm.

Sunday: 11am, 1pm, 3pm, 5pm

As of this writing, we are booked through April 20th. We will expand our hours ASAP. In the meantime, you may book your future float through our online calendar (hover over the date to see the popup calendar for a specific date) or ask to be added to our automated wait list.

Current status: limited open

Get ready to float!

We’re opening our calendar in stages, starting Wednesday, February 25th. In our crowdfunding campaign last fall, we promised our backers that they could get in to the tanks first. So:

1) First shot goes to our crowdfund backers: check your email at noon on Wednesday the 25th.

2) Everyone who preordered should check their email at noon on Saturday the 28th.

Our calendar will be open to everyone on Wednesday, March 4th!

Thank you, everyone, for your patience and ongoing support! It means so much to us.

Construction progress 4

We are so close to being finished! The place is starting to look like something real. Our contractor is down to the last little details, and we’ve turned our attention from structural things like ceilings and walls, to putting together a whole lot of IKEA cabinets and furniture… and building the tanks themselves!

The Escape Pod tanks are built; an inspector came out to look at our setup and gave our guys a few notes and changes to make. They got right to work on that, and we’re one step closer to our general inspection. We’re waiting for our electrician to wire the pumps and then we’ll plug it all in. I made a gif of the building process… Continue reading Construction progress 4

Construction progress 2

A piece of bad news to lead off with: after delays with inspections, some extra work from surprises in the walls, and scheduling problems over the holidays, our contractors our now saying they expect to be finished in early February.

The work so far is looking great, though.  Electrical and plumbing roughin inspections are both signed off, and we’ll be closing up the walls next week.

For several days after the electricians started, there were tangles of armored cable everywhere, like Doctor Octopus had just lost a fight.
For several days after the electricians started, there were tangles of armored cable everywhere, like Doctor Octopus had just lost a fight.

 

Float tank delivery
Our first two new float tanks arrived in the rain right before Christmas.

Continue reading Construction progress 2